News > Jiangsu Sailboat 01.11.2016
Jiangsu Sailboat Tubular HPU onsite
service (01.11.2016)
Onsite service for Jiangsu Sailboat Tubular HPU has been successfully
performed. During 8 days of commissioning (Oct 25, 2016-November 1,
2016), we have filled nitrogen in local accumulator manifold skid and
both back up stations, and all pressure reached above 135bar, filled
the tank with lubricate oil, pressurized all the piping from HPU to
local accumulator manifold skid, checked and tested all the
instruments in HPU to make sure all the signals are well received in
DCS, successfully flushed the whole system.